Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 exam Name the components of Work Breakdown Structure, Network and activities, Milestones Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement and Describe procedures for establishing budgets and r. If you want to prepare C_TPLM22_64 exam in short time then you can get latest Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 exam questions similar to actual C_TPLM22_64 exam. Practicetestguru provide you C_TPLM22_64 dumps in two formats. You can prepare well through PDF Q&A booklet and C_TPLM22_64 exam practice test software with confidence to succeed by saving your time and money both.

♥ VALID C_TPLM22_64 Exam Questions 2018 ♥

C_TPLM22_64 exam questions, C_TPLM22_64 PDF dumps; C_TPLM22_64 exam dumps:: https://www.dumpsschool.com/C_TPLM22_64-exam-dumps.html (100 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest and Most Accurate SAP C_TPLM22_64 Dumps Exam Questions and Answers:

Version: 5.0
Question: 21

What are the various options available for creating a WBS BOM?
There are 2 correct answers to this question.
Response:

A. Copying a Material BOM
B. Copying a sales order BOM
C. Copying other WBS BOM
D. BOM copy function

Answer: AC

Question: 22

Which of the following decides whether networks can be header assigned or activity-assigned?
There are 2 correct answers to this question.
Response:

A. Order type
B. Plant
C. Billing type
D. Network structure

Answer: AB

Question: 23

What are the components on which reporting is based upon, in profit center accounting?
There are 2 correct answers to this question.
Response:

A. Cost centers
B. Cost elements
C. Profit centers
D. Profit center hierarchy

Answer: CD

Question: 24

Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?
Please choose the correct answer.
Response:

A. Contractual management
B. Claim management
C. Claim Planning
D. Variance management

Answer: B

Question: 25

Which of the following specifies how much time must elapse between individual archiving steps in network type?
Please choose the correct answer.
Response:

A. Functional areas
B. Residence times
C. Classification indicator
D. Functional areas

Answer: B

Question: 26

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?
There are 2 correct answers to this question.
Response:

A. Billing element
B. Cost element
C. Pricing element
D. Account assignment element

Answer: AD